HMPL Boiler Furnace Rebuild

Western Kentucky Energy

Western KY

To overcome the many obstacles in meeting the aggressive eight week outage schedule, Titan Contracting & Leasing developed an innovative way to approach a major water wall rebuild that had limited access by installing a Derrick crane onto one of the adjacent boilers during the pre-outage.

Titan’s Scope included replacing 75% of this 190 megawatt boiler water wall in fifty-two panels for a total of 2190 tube welds. Titan was successful in obtaining a dry hydro-test after the chemical clean.