LP Evaporator / Economizer Modules

Progress Energy

Bartow, Florida

During a four week outage, Titan Contracting & Leasing removed and replaced the LP evaporator/econimizer modules on two HRSG units. Along with removal of the existing steam drums and modules, Titan installed new 178 ton modules, reinstalled the steam drums and platforms, and completed all interconnecting welds on top of the unit, as well as the drain lines under each unit.