Wilson Outage
Big Rivers Electric Corporation
Western KY
Titan Contracting & Leasing staffed this aggressive outage at a Western KY power plant replacing the super heat elements, air basket and seal change out, replacement and extensive repairs on the AQCS equipment and extensive ductwork repair.
The outage had a six week duration with a peak work force of 430 working a total of 161,000 man-hours.